Department | Warehouse | Document no | WAR-060 | ||
Prepared by: | Date: | Supersedes: | |||
Checked by: | Date: | Date Issued: | |||
Approved by: | Date: | Review Date: |
Document Owner
Warehouse Manager
Affected Parties
All warehouse staffs working in the dispensing operations.
Purpose
To outline the measures to be taken to ensure the safety of all goods and personnel when using the storage racking system in order to avoid injury to staff or damage to property.
Scope
It is the responsibility of all staff involved with the handling and storage of materials or product to follow the requirements of this SOP and report any damage which may be incurred. This SOP particularly relates to the activities of the staff of the Receiving and Distribution Warehouse.
Definition
DR | Deviation Report |
Related Documents
Form-115 | Warehouse Racking Check List |
Form-110 | Pallet Racking Damage Log Form |
QMS-035 | Deviation Report System |
EHS Statement
Safety clips are positioned to ensure that the support beams are in place.
Any damage is to be reported immediately.
Procedure
1. New Employees
All new personal employed to work in the Receiving Warehouse are to be appropriately trained in order to understand the importance of storage racking safety and follow the procedure when working within any pallet racking system.
Any time you accidentally run into any part of the pallet racking there is to be an EHS Deviation Report raised and an investigation into the damage carried out, and any damage is to be reported on Form-110.
2.1. Major Impact into the Racking:
If extensive damage occurs during normal duties, personnel are not to step out of the forklift to assess the damage. Personnel are to:
2.1.1. Stay within the forklift, drive away and notify all Warehouse personnel and the Area Manager immediately.
2.1.2. The Warehouse person who made the impact, with another staff member, will investigate the area immediately after the impact.
2.1.3. Secure the area by sectioning off and removing stock that is damaged from the racking. Be sure to empty the whole bay. (Do Bulk-to-Bulk transfers). If a support beam is damaged both bays either side of the damaged upright are to be emptied.
2.1.4. A EHS DR is to be raised – see SOP QMS-035
2.1.5. The racking supplier is to be notified of the pending repair.
2.1.6. Fill in Form-110.
2.2. Minor Impact into the Racking:
If minor damage occurs during normal duties:
2.2.1. The Racking does not need to be emptied.
2.2.2. A DR is to be raised.
2.2.3. The Area Manager is to be notified in order to arrange a repair.
2.2.4. If it is a cross beam which has being damaged, the Storeperson can empty that bay and replace with spare racking the warehouse have available – as long as it is placed in the same area.
2.2.5. Fill in Form-110.
2.3. If safety clip is dislodged or broken during normal duties:
2.3.1. Goods must not be placed on that rack until the safety clip is replaced. This should be completed immediately. It is the responsibility of the warehouse staff to infor and replace the safety clip straight away.
2.3.2. If no safety clips are on site, the area must be sectioned off and not used until more clips are supplied..
All Warehouse staff must be notified not to use the area until further notice.
2.3.3. If there are no safety clips on site, fill in Form-110.
3.1. Safety clips are positioned to ensure that the racking support beams are in place. All safety clips and racking (both cross-beams, side supports and safety guarding rails) are to be checked by Warehouse personnel on a monthly basis, as per Form-115. The Warehouse Manager needs to ensure that the Warehouse staff check all the racking in all areas at the beginning of each month, using the following procedure:
3.1.1. By looking at each rack, determine if all the safety clips are in place. Two members of the warehouse team will be lifted in the safety cage by a third team member who will then drive the forklift through each row of racking.
3.1.2. If there are any clips missing, these need to be replaced straight away.
3.1.3. Once the safety clip/s has been replaced the Form-115 is signed to signify that the replacement has occurred.
3.1.4. If there are any damaged beams or side supports or damage to safety guarding/rails – they need to be identified and logged in the existing Form-115 and, if it is extensive damage, fill in Form-110
3.1.5. All racking layouts are to remain the same. They can only be changed with the assistance and advice of a contract Racking Systems representative.
4. Yearly Audit
External Auditors will be brought in to inspect all the racking annually. A Report will be filed in Racking Log File.
5. Summary of Changes
Version # | Revision History |
WAR-060 | New |